Mill Lake Dam Rehabilitation (2009) Mill Creek Irrigation District (MCID)
Mill Lake Dam History
|
|
Project History Since construction, the dam has had numerous rehabilitation projects, including major rehabilation in 1922, 1944, 1959, 1960, 1961, 1964, 1991 and 1992. Recently, the dam has had some serious concerns and in 2001, an emergency repair was completed and funded by a DNRC grant. In 2002, temporary slip lining of the outlet pipe occurred. In 2005, permanent slip lining was completed on the outlet pipe, funded by a DNRC grant. In 2007, a rehabilitation project (Phase I) was completed which consisted of rock berm construction, downstream dam crest edge stability construction, and AMCi® satellite alarm system. This rehabilitation was paid for by the Mill Creek Irrigation District. To complete the final phase of rehabilitation, the District looked for assistance from loans. |
|
Work Breakdown
|
|
Project Funding The total cost of the project was $603,726. To finance the project, the Mill Creek Irrigation District used the following loan program:
|
|
Project Status & Results
Project Partners Owner: Mill Creek Irrigation District Lead Design Engineer: Hydrometrics Prime Contractor: Land Tech Montana Inc. |